Quote:
Originally Posted by "W"
In perfect world case !!! One removal we just did cost about 2.3 mill
Work needed cost about 1.8 mill
When a well is made you have money allocated for removal of that platform, a abandon platform is sitting in saltwater !!
Now if you had a 2 pile structure that would cost 10mill to remove it could be worth the delay, but when ot starts rusting up the repair damage will cost in the millions also!
The platform on that vid cost about 500,000 in PNA and about 1.5 to remove , which money has already been allocated for that!
|
See my post above, you are saying companies want the government to tell them when they have to do something. If it were better to blow rigs up the day a rig become a dry hole or is non productive then why were there rigs just sitting out in the gulf for 10+ years?
I'm done with the thread, you need alot more tools than you have for us to have this conversation.