Speck as givemeabreak and myself have indicated a surveyor or engineer is going to have to provide a certified post construction finished floor or low structural member elevation on your flood elevation certificate which is going to be required by the local building and flood official. Without the completed certificate the parish building official will not give clearance to the power company to turn on permanent power to your structure. If financed your lending agency will also require a completed elevation certificate prior to initiating your permanent mortgage loan.